SIGA Innovation Center

All the latest news about the Project ist available here


Published on the 26th of November 2018

Approved for production

We are delighted! The new production hall has been opened and released for production with one first pallet - provided with a little surprise.

 

The final important planning decisions were also made.The technical installations in the new office building are running at top speed.

 

Roofs. PV plant. Wooden frontage. Everything is setup. Now, only the PV frontage elements have to be assembled. Work on surroundings should be finished before the onset of winter as well.



Published on the 7th of September 2018

Topping out ceremony

The shell of the new innovation centre is now complete, and on September 6 we celebrated that together with an apéro and a midday meal. SIGA CTO Daniel Schmid welcomed the guests, with heartfelt thanks all round to all those who contributed to the work for their great efforts and good cooperation.



Published on the 3rd of July 2018

The production hall is up

Due to the favorable weather conditions the new production hall could be

built up within a short time. This was possible, particularly because of the

close collaboration between timber builders, roofers and window fitters etc.

Thank you very much!



Published on the 18th of May 2018

Craftsmen breakfast

SIGA invites to a joint breakfast. On this occasion Patrick Haacke, CSO, introduces SIGA briefly to the guests. Rafael Hunziker, head of the project site development, thanks the craftsmen for the big effort and for the good cooperation. As a surprise every participant gets a SIGA bag with a tape measure, a cutter, a pen and a role SIGA Rissan. And of course a Ricola can not be missing!



Published on the 10th of May 2018

Aerial images

These photographs by drone show impressively how tall the construction is growing.



Published on 22 March 2018

The innovation centre is getting bigger

The first and second floor and the loading docks for the lorries are concreted.The base plate for the new production is growing as well.



Published on 19 February 2018

Construction is advancing quickly

First walls are up. The innovation centre is growing taller. The planning of the inner

design is in progress as well.

 



Published on 24 January 2018

The SIGA innovation centre is taking shape

The small building of the new transformer station for the current supply is built with bricks.

 

 



Published on 11 December 2017

Building site update

The first construction phase was realized according to schedule.



Published on 27 September 2017

The groundbreaking ceremony is completed

The groundbreaking ceremony for project worth 30 million Swiss francs took place on Wednesday 27 September.



Published on 30 August 2017

Interview with Rafael Hunziker, Project manager

Rafael Hunziker has been working as an engineering project manager at SIGA since 2014. He has been responsible for the Schachen site development project since spring 2016. The project enters an important phase with the submission of the planning application at the start of June.




Published on 15 August 2017

A flavour of the day-to-day construction work

 

Planning application submitted. The scaffolding is up.

 

 



Published on 13 July 2017

Planning application

The new development of SIGA's innovation centre enters an important phase. The planning application was submitted to the municipality at the start of June and we expect building approval around mid September.



working at SIGA

WebCam

Media Release



 

If you have any questions about our construction project, please contact us..